Armstrong Road – Iron Horse Drive Pipeline Project

The Armstrong Road – Iron Horse Drive Pipeline Project was completed in the fall of 2019.  Remaining chip seal and other pavement improvements were completed in May and June of 2020 on Iron Horse Drive and Brewer Road. Paving of Armstrong Road was completed at the end of 2019.

The project included the extension of the District’s treated water main from the start of Armstrong Road running northward, along the entirety of Iron Horse Drive, and easterly along Brewer Road up to Eggbert Hill Road.  The installed pipe is 8-inches in diameter and approximately 7,200 feet long including individual service boxes and fire hydrants.